BASIC TIME CALCULATION
SHIFT DURATION = 8 HRS
WORKING HRS = 7HRS
WORKING MINITUS PER DAY = 420 min
PRODUCTION TARGET = 1000 UNITS
PRODUCTION TARGET PE/ WEEK = 6000 UNITS
WORKING MINITUS PER WEEK = 420X 6 = 2520 min
DETAILS ABOUT ASSEMBLY LINE
SEQUENTIAL DIAGRAM
TASK TIME
TOTAL TASK TIME = ∑ (SUM OF ALL THE
STATION CYCLE TIME)
TOTAL
TASK TIME = ∑ (11.9 + 15.8 + 28.4 + 6.48........+
120.6+184.6)
TOTAL TASK TIME = 881.98 SEC
CYCLE TIME REQUIRED = (PRODUCTION TIME PER DAY) / (UNIT REQUIRED PER DAY)
= (420)/(100)
= 4.2 MIN
NUMBER OF WORK STATION NEEDED = (TOTAL TASK TIME) / (CYCLE
TIME)
= 881.98/42
= 20.9 ≈ 21 STATIONS
LINE EFFICIENCY = (SUM OF TOTAL TASK TIME ) / (NO OF WORK
STATIONS X 60 SEC)
X 100
=(881.98)/(21*60)*100
=70%
BALANCED DELAY EFFIENCY = (100%
- LINE EFFICIENCY)
= 100% -
70% = 30 %
(Not possible to achieve 100 efficiency)
LABOUR PRODUCTIVITY = (LABOUR WORKING HOURS PER
WEEK) / (UNIT PRODUCED PER WEEK) X100
=(42*60) / (6000)
=42%